B.1 Construction Sequence

  1. Apply for and pick up any right of way permits from Kitsap County Department of Public Works (KCPW).

  2. Construct stabilized construction entrance(s).

  3. Construct silt fence barriers.

  4. Construct sedimentation basins.

  5. Construct runoff interception and diversion ditches.

  6. Clear and grade the minimum site area required for construction of the various phases of work.

  7. Provide temporary hydroseeding or other source control stabilization measures on all disturbed soils.

  8. Maintain all erosion and sedimentation control best management practices (BMPs) to provide the required protection of downstream water quality.

  9. All catch basins and conveyance lines shall be cleaned prior to paving. The cleaning operation shall not flush sediment laden water into the downstream system.

  10. Provide permanent site stabilization.

  11. Erosion and sedimentation control BMPs shall not be removed until construction is complete and accepted by Kitsap County.