B.2
Drainage Notes
-
The contractor shall ensure that the drainage is installed and operational prior to commencement of paving work.
-
All steel pipe and parts shall be galvanized. All submerged steel pipes and parts shall be galvanized and have asphalt treatment #1 or better.
-
Drainage stub-outs on individual lots shall be located with a 5‑foot‑high 2" x 4" stake marked "STORM." The stub out shall extend above surface level and be secured to the stake.
-
Video documentation of pipe interior for alignment and joint connection adequacy shall be provided if not inspected prior to cover.