B.2 Drainage Notes

  1. The contractor shall ensure that the drainage is installed and operational prior to commencement of paving work.

  2. All steel pipe and parts shall be galvanized. All submerged steel pipes and parts shall be galvanized and have asphalt treatment #1 or better.

  3. Drainage stub-outs on individual lots shall be located with a 5‑foot‑high 2" x 4" stake marked "STORM." The stub out shall extend above surface level and be secured to the stake.

  4. Video documentation of pipe interior for alignment and joint connection adequacy shall be provided if not inspected prior to cover.